How Long Does an ADU Permit Take in Marin County?
Every Marin jurisdiction works to the same state rule: a decision within 60 days of a complete application. The county's own permit records show how long owners actually waited.
The short answer
A median of 205 days — just under seven months — from application to permit issued, across 189 standalone ADU permits in unincorporated Marin. In Mill Valley, 186 days across 12 permits.
- The middle half of county permits took 132 to 308 days.
- Only 3 of 189 were issued within 60 days of applying. Fewer than half (82) were issued within six months.
- Garage conversions were the quickest type: a median of 162 days (18 permits). Detached new ADUs: 207 days (53 permits).
- San Rafael publishes no per-permit data, so we show no San Rafael figure and borrow none.
These are records of past permits, not a forecast for yours.
Sources, as of November 2026: Marin County open-data building permit records (dataset mkbn-caye), ADU permits issued Jan 2023–Nov 2026, 256 records of which 189 are standalone ADU permits; City of Mill Valley monthly "Permits Issued with Fees and Values" reports, Sep 2025–Sep 2026 (11 of 13 months published); California HCD Annual Progress Report Table A2 (permits issued 2018–2023); Gov. Code §§66310–66342, SB 543, AB 462, AB 1332; Marin County Development Code §22.32.120; Marin Water Code §11.56.040(h). Medians computed by ADU Build Works; method at About.
The county record
189 permits, one table
Unincorporated Marin covers the places outside city limits — Kentfield, Greenbrae, Tam Valley and Strawberry (which carry Mill Valley addresses), Lucas Valley and Santa Venetia (San Rafael addresses), and West Marin from Stinson Beach to Tomales. For every standalone ADU permit the county issued from January 2023 to early November 2026, we counted the days from application to issuance.
| Issued within… | Permits (of 189) | Share |
|---|---|---|
| 60 days of applying | 3 | 2% |
| 90 days | 17 | 9% |
| 120 days | 35 | 19% |
| 180 days (about six months) | 82 | 43% |
| 365 days (one year) | 158 | 84% |
| 730 days (two years) | 179 | 95% |
Thirty-one took longer than a year. Ten took longer than two. The quickest was issued in 7 days; the slowest took 1,469.
One limit you should know about. The county's file lists permits that were issued. It does not list applications that are still open or were abandoned, so this table describes the projects that made it through — the true picture for everyone who applied is somewhat slower than this.
The measure also includes both sides' time: the county's review, and the weeks an applicant's designer spent answering comments. The record does not split them.
By project type
Which kind of ADU got its permit fastest?
| ADU type (from the permit description) | Median days | Middle half | Permits |
|---|---|---|---|
| Garage conversion | 162 | 128–242 | 18 |
| Attached ADU | 172 | 123–283 | 22 |
| Junior ADU | 187 | 108–318 | 19 |
| Conversion of other existing space | 203 | 140–312 | 38 |
| Detached new ADU | 207 | 141–284 | 53 |
| Type not clear from the description | 240 | — | 39 |
The order is roughly what you would expect — work inside an existing structure moved a little faster than a new building — but the gap is about six weeks, not six months. Choosing a conversion over a detached unit is a sound way to cut cost. On this record it is only a modest way to cut the permit wait.
The "middle half" column matters more than the median. A garage conversion at the slow end of its middle half (242 days) took longer than a detached ADU at the fast end of its own (141 days). Your lot and your application decide more than your ADU type does.
By filing year
The trend looks good. Read it carefully.
| Year applied | Median days to issuance | Permits |
|---|---|---|
| 2021 | 759 | 6 |
| 2022 | 310 | 28 |
| 2023 | 229.5 | 44 |
| 2024 | 204 | 44 |
| 2025 | 156 | 47 |
| 2026 | 137.5 | 20 |
Two things are going on, and only one of them is good news.
The illusion. Our file starts with permits issued in January 2023. An application from 2021 could only be in it if it took more than a year — so the 2021 and 2022 rows are slow by construction. At the other end, a 2026 application can only be in it if it was issued fast; the slow ones are still open. Both ends of the table are bent.
The part that may be real. The 2023 and 2024 rows are the least distorted, and they sit at 230 and 204 days. That is the fairest reading of "normal" for the county: roughly seven months at the median. Whether 2025 and 2026 are truly faster will only be clear once their slow permits are issued and counted.
Mill Valley
Inside city limits: 186 days, on a small sample
The City of Mill Valley publishes a monthly list of permits issued. In the eleven monthly reports available from September 2025 to September 2026, we found 12 standalone ADU permits.
- Median, application to issuance: 186 days. Middle half: 130 to 259 days.
- Quickest 62 days; slowest 710. Five of the 12 were issued within six months, and 11 of the 12 within a year.
- By type: six detached ADUs at a median of about 186 days, and four conversions at 174.
Twelve permits is a small sample. It is enough to say that Mill Valley's wait has looked like the county's — it is not enough to rank the two.
Mill Valley has one fork worth knowing before you design. An ADU that meets the city's objective standards is approved by staff. One that does not — the city's own example is a 1,096 sq ft unit at 19 ft 11 in — goes to discretionary review and a public hearing. And a conversion that needs more than 50 cubic yards of excavation, or a raised roof, can lose its conversion status. Details: Mill Valley ADU rules.
San Rafael, Novato and the other towns
San Rafael publishes no bulk per-permit data, so there is no San Rafael median here. We have not yet measured Novato, Tiburon, Larkspur or the other towns either. Where we have no record we say so; we do not stretch the county's number over a town it does not cover. What is the same everywhere is the state rule below.
The 60-day rule
What state law guarantees — and what it leaves out
The guarantee. Every Marin jurisdiction must approve or deny a complete ADU application within 60 days, by staff, with no hearing — or within 30 days if you use a plan the jurisdiction has already pre-approved. No Marin jurisdiction publishes a faster local promise.
The catch. The 60 days run from a complete application, and stop at the decision. Getting to "complete," and getting from "approved" to "issued," sit outside the clock.
The 2026 fix. Under SB 543, since January 1, 2026 a jurisdiction has 15 business days to rule your application complete or give you a list of what is missing, and another 15 business days for each resubmittal. Silence means the application is deemed complete — not approved — and the 60 days begin.
Pre-approved plans. State law cuts the decision to 30 days for a detached ADU on a pre-approved plan. As of November 4, 2026, Marin County had not posted a catalogue of its own pre-approved plans; the programme was still in development. ADU Marin (adumarin.org), the free service every Marin jurisdiction points owners to, is the place to ask what is currently accepted where.
What slows a Marin permit
Six things that pull a project out of the fast lane
The permit record does not give reasons. The county's code and decisions do tell us where a simple ADU stops being simple.
- Planned districts, ridgelines, stream areas and the coast. In unincorporated Marin, a state-exempt ADU is itself approved without design review. But in a Planned (P) district, on a ridgeline, in a Stream Conservation Area or in the coastal zone, other work proposed alongside it can be pulled into Design Review even when the ADU itself is not.
- The coastal zone. A coastal permit is still required. Since October 2025, state law gives the local agency 60 days to decide a complete coastal permit application for an ADU, and the local decision can no longer be appealed to the Coastal Commission. That shortens the tail; it does not remove the permit.
- Size above the guaranteed envelope. A detached ADU up to 800 sq ft, 16 ft high, 4 ft from side and rear lines is guaranteed by state law. Past that, you are relying on local standards, and in some towns a hearing.
- Water. In the Marin Water district, a qualifying ADU needs no new water service — but the district reviews a Project Information Form first, which it says takes 10 to 14 business days. File it early, in parallel.
- Septic. On a septic lot, whether the system can serve another unit is a separate question with its own review. Many West Marin lots are on septic, so ask this first there.
- Incomplete first submittals. The only delay entirely in your team's hands.
The fee-waiver clock
If you are racing December 31, 2026
In unincorporated Marin, the county waives up to $2,500 in fees per ADU and $1,500 per junior ADU, on a programme that runs through December 31, 2026.
What must happen by that date is unconfirmed. The county's published programme does not say whether the qualifying event is an application, an issued permit, or something else. Confirm it with Marin County's Community Development Agency before you rely on it.
Here is why the answer matters. If the trigger is an application on file, you have until late December. If it is an issued permit, the record is blunt: 3 of 189 county ADU permits were issued within 60 days of applying. Plan for the stricter reading until the county tells you otherwise. Full detail: Marin ADU fee waiver.
After the permit
The build: 440 days in the county, 502 in Mill Valley
State housing records track a second span — from the day a permit is issued to the day the unit is recorded complete. For ADUs permitted from 2018 to 2023:
| Jurisdiction | Median days, permit to completion | Middle half | Projects |
|---|---|---|---|
| Unincorporated Marin | 440 | 222–729 | 123 |
| Mill Valley | 502 | 349–734 | 50 |
| San Rafael | Being re-verified — not shown | — | — |
These come from different projects and different years than the permit waits above, so we never add the two together. Side by side, they say this much: in Marin the build has typically taken about twice as long as the permit.
Ready to start
If you plan to apply this winter
- Check the lot first. Town or unincorporated, sewer or septic, slope, fire zone, coastal zone. The lot checker below does it in about a minute.
- Design to the guaranteed envelope if speed matters more than size.
- Ask whether a pre-approved plan is accepted in your jurisdiction. Where one is, the law's 30-day decision applies.
- File the water form and any septic review in parallel, not after planning approval.
- Submit a complete application and ask for the completeness ruling in writing. The 15-business-day answer is your right since 2026.
- Line up your builder during review. Bids take weeks; get them on the same drawings while the permit is pending. Start with how to vet a Marin ADU builder and the quote comparison worksheet.
Questions, answered
Marin ADU permit timing: quick answers
How long does an ADU permit take in Marin County?
In unincorporated Marin, a median of 205 days from application to issuance across 189 standalone ADU permits issued from 2023 to November 2026. The middle half took 132 to 308 days.
How long does an ADU permit take in Mill Valley?
A median of 186 days across the 12 standalone ADU permits in the city's monthly reports from September 2025 to September 2026. It is a small sample; the middle half took 130 to 259 days.
Why isn't it 60 days?
The state's 60-day clock runs from a complete application to the decision. Time spent getting the application complete, and between approval and issuance, is outside it. Only 3 of 189 county permits were issued within 60 days of applying.
Which type of ADU is fastest to permit in Marin?
On the county record, garage conversions: a median of 162 days across 18 permits. Detached ADUs took 207 days across 53. The spread inside each type is wider than the gap between them.
How long does it take to build an ADU in Marin once permitted?
State records show a median of 440 days from permit to completion in unincorporated Marin (123 projects) and 502 days in Mill Valley (50 projects), for permits issued 2018–2023.
Is there a San Rafael figure?
No. San Rafael publishes no bulk per-permit data, and its state-reported build figure is being re-verified, so we show neither.
Can a builder promise me a permit date?
No one can. A builder or designer can show you permit numbers for past Marin projects, and you can look up how long those took.
Keep going
Related Marin guides
Marin County
ADU builders in Marin: how to vet and compare
Licence checks and comparable bids.
Marin County
Garage conversion ADU in Marin
The fastest type on the county record.
Marin County
Marin ADU fee waiver
Up to $2,500, programme ends Dec 31, 2026.
Marin costs
ADU cost in Marin County
Planning ranges by type.
Check your lot
Find out what your lot adds to the clock
Type your address and tap twice. You get a plain-language verdict on screen — what your lot can likely take, and the flags that slow a permit — before we ask for any contact details. If you choose to save your brief, we store it and tell you so. No builders are signed to our roster yet, so no quotes are available today and no builder will contact you.
Check my lot
FREE · FAST VERDICTStep 1 of 2 — your address, what kind of home it is, and what you want to build. Two taps. That is enough for a first verdict; sharpen it afterwards only if you want to.
Stored and confirmed
Anything wrong in that summary? Email us at [email protected] and we'll correct the record.
We already have this brief from you
If something changed — a different project, a new budget — email us at [email protected] and we'll update the record. Your verdict itself is above, and it stays yours.
That didn't go through — nothing was sent
Your verdict is right here on this page, and it stays yours. Prefer to do this by email? Write to us at [email protected] with your address and what you'd like to build, and we'll set it up with you — no dead end.
Every type, answered — not just the one you picked
True cost — the planning band, the fees on record, and what the band leaves out
Not in the band — budget these separately; no honest source lets us put a number on them for your lot, so none is invented:
How long until someone can move in?
Dates that change this decision
What the permit record shows
What would change this answer
Lay your quotes side by side
Print this sheet and write each contractor's figures in a column. Every row is something a comparable bid has to state; a blank in a quote is a question for that contractor, not a saving. The first column is your brief, filled from your answers.
| Line every quote must state | Your brief | Quote A | Quote B | Quote C |
|---|
Check each contractor's licence number on the Contractors State License Board's public lookup (cslb.ca.gov) before you compare prices. Figures in your brief are the rule caps and planning estimates shown above, not bids.
Make your verdict more exact (optional)
Skip these — save my brief ↑San Francisco screening — two questions that decide an SF project
In San Francisco, space a tenant uses can be a protected “housing service” — it changes what’s allowed, so we ask now, not later. Why this matters →