How to Compare ADU Quotes, Line by Line

You have two or three ADU bids on the table and the totals are far apart. Before you pick the lowest, find out whether they are prices for the same project. Usually they are not.

The short answer

Do not compare totals. Put every bid onto the same 13 lines, and compare line against line. A line a builder leaves blank is a cost you will meet later.

  • Lines 1–2 fix the project: the same ADU type, size and storeys in every bid.
  • Lines 3–7 fix the money: construction, design and permits, site work, fees, and what is excluded.
  • Lines 8–9 fix the terms: the schedule, and payments tied to finished work.
  • Lines 10–13 fix the risk: licence, insurance, warranty, and the conditions your lot must clear first.

Print this page, or copy the table into a spreadsheet. It works for any builder, anywhere in the Bay Area — you do not need us to use it.

Sources, as of November 2026: the comparison sheet built into the ADU Build Works lot checker (the same 13 lines appear on every saved brief); the four cost buckets defined at ADU cost in Marin County; Contractors State License Board licence lookup and consumer guidance at cslb.ca.gov. This page gives no price figures and is not legal advice.

Check this for your address — free

Type your address and tap twice. You see your verdict on screen before we ask for any contact details.

No phone number needed. No builders are signed to our roster yet — we tell you that before you save anything.

The worksheet

The 13-line ADU bid comparison sheet

Fill one column per builder. Write the figure or the words the bid actually uses. If the bid is silent on a line, write "not stated" — and ask.

#LineBid ABid BBid C
1Scope and ADU type, in one written description
2Size (sq ft) and storeys
3Construction price
4Design, engineering and permit drawings
5Site work and utilities
6Fees (city, county, school, utility) — included, or owner pays?
7Allowances and exclusions
8Schedule: start date to final inspection
9Payment schedule, tied to completed work
10CSLB licence number (verified at cslb.ca.gov)
11Insurance: general liability and workers' compensation
12Warranty: what is covered, and for how long
13Conditions the lot must clear before the price holds

When the sheet is full, the real comparison is usually obvious. The "cheap" bid is often the one with three blank lines.

Lines 1–2

First, make sure everyone priced the same building

The most common reason two bids differ is that they describe different projects. One builder priced a 600 sq ft one-bedroom; another heard "ADU" and priced a studio. One assumed a slab; another assumed a raised floor on a slope.

What to do. Write the project down once, in a paragraph, and send the same paragraph to every builder: the ADU type (detached, attached, garage conversion, junior ADU, basement conversion), the size, the number of storeys, bedrooms and bathrooms, the finish level, and what you know about the lot. If you have drawings, every builder bids the same set.

This is what the brief from our lot checker is for: one written description of your lot and project that every builder can price against, so the bids come back comparable.

The test. Read line 1 across the row. If the three descriptions would not produce the same building, stop — you are not ready to compare prices yet.

Lines 3–7

Then split the money into the same buckets

A single lump sum cannot be compared with anything. Ask for the price in separate parts, and put each part on its own line.

Line 3 — Construction price

The building itself: foundation, framing, roof, exterior, insulation, plumbing, electrical, kitchen, bathroom, finishes. Ask whether it is a fixed price or an estimate, and what would change it.

Line 4 — Design, engineering and permit drawings

Architectural plans, structural engineering, energy calculations, surveys, and any report your lot needs. Some builders include all of it. Some assume you arrive with stamped drawings. Neither is wrong — but one bid includes tens of hours of professional work and the other does not.

Line 5 — Site work and utilities

Grading, drainage, retaining walls, trenching, and the water, sewer, gas and electrical runs to the unit — including a panel upgrade if the house needs one. On a flat lot with services nearby this line is modest. On a slope, on septic, or with a long run from the street, it can decide the project. A bid that says "site work by owner" or "utilities excluded" has left out the least predictable cost on the sheet.

Line 6 — Fees

Plan check, building permit, impact fees, school fees, utility connection charges. Ask one question: are fees inside your number, or do I pay them directly on top? Either answer is fine. Not knowing is not.

Line 7 — Allowances and exclusions

An allowance is a placeholder — "$X for cabinets" — that becomes a change order when the real thing costs more. An exclusion is something the builder is telling you they are not doing. Read both lists side by side. Ask each builder to price the items the others included.

The test. Add lines 3 to 6 for each bid, then read line 7. Only now do you have totals worth comparing.

Lines 8–9

Schedule and payments: the terms that protect you mid-project

Line 8 — Schedule

Ask for two dates and one condition: the start date, the date of final inspection, and what the start depends on (permit issued, drawings approved, a deposit). A builder who gives a duration but no start date has told you nothing about when you will have a finished unit.

Ask, too, how many ADUs the builder has finished in your town and for the permit numbers. Permit records are public; you can check how long those projects took.

Line 9 — Payment schedule

Payments should follow finished work — foundation complete, framing complete, rough inspections passed — not calendar dates. California law caps the down payment on a home-improvement contract. The Contractors State License Board publishes the current cap, and its guidance on progress payments, at cslb.ca.gov; check it before you are asked for a deposit.

The test. If you stopped the project after any payment, would the work in place be worth roughly what you had paid? If a schedule fails that test, ask for it to be re-staged.

Lines 10–13

Licence, insurance, warranty and the fine print about your lot

Line 10 — The licence

Every bid should carry a CSLB licence number. Look it up yourself at cslb.ca.gov. Check that the licence is active, that the name matches the contract, that the classification covers the work, and whether any complaints or disciplinary actions are disclosed. It takes five minutes and it is the cheapest due diligence on the sheet. Our fuller walk-through: how to vet an ADU builder.

Line 11 — Insurance

Two policies: general liability, and workers' compensation. The CSLB record shows whether workers' compensation is on file or whether the contractor has declared no employees — which matters if a crew turns up. Ask for a certificate of insurance naming you.

Line 12 — Warranty

What is covered, for how long, and who you call. A written warranty on workmanship is separate from the manufacturers' warranties on the products.

Line 13 — Conditions the lot must clear

Most bids are conditional: "subject to soils report," "assumes existing sewer lateral is adequate," "assumes no design review." These are not small print. Each one is a point where the price can move after you have signed. List them, and ask what each would cost if it went the wrong way.

Our lot checker flags the common ones for your address — slope, septic, fire zone, coastal zone, design review, and in San Francisco the tenant and rent-control questions — so you can raise them before the bid, not after.

Reading the result

Seven signs a bid is not ready to sign

  1. A single lump sum with no breakdown.
  2. Line 5 blank — site work and utilities "to be determined."
  3. Fees unmentioned.
  4. Allowances for most of the finishes, so the real price is unknown.
  5. A deposit request before a written contract, or a large first payment before any work.
  6. A promised permit date. Nobody controls the permit office.
  7. Pressure to sign today. A real price holds long enough for you to check a licence.

And three signs of a good one: it answers every line without being asked twice; it tells you what it excludes; and the builder is willing to see the other bids' scope and price the difference.

Before you ask for quotes

What makes a builder take your request seriously

A builder can only price what you can describe. Owners who arrive with the six items below get bids that can be compared; owners who do not get guesses. Have these in hand:

  • The address and jurisdiction — city, or unincorporated county.
  • What you want to build, in one paragraph (line 1 of the sheet).
  • What it is for — family, rental, or resale value — because it changes the design.
  • Your budget range and how it is funded. A builder cannot design to a number you will not say.
  • Your timing. "Ready to start design now" and "sometime in the next two years" are different conversations.
  • What you already know about the lot — slope, septic, fire zone, tenants.

The lot checker asks exactly these questions and puts the answers on one page with this 13-line sheet attached.

Where we stand, plainly. ADU Build Works plans to introduce owners to at most three licensed builders per territory. As of November 2026 no builder is signed to our roster, so we cannot get you quotes today. The sheet above is free to use with any builder you find yourself.

Questions, answered

Comparing ADU bids: quick answers

How many ADU quotes should I get?

Two or three that describe the same project. More than that rarely adds information, and it is a lot of builders' unpaid time to ask for.

Why are my ADU quotes so far apart?

Usually because they price different things: a different size or finish level, design and permits included in one and not the other, or site work and fees left out. Put each bid on the 13 lines and the gap usually explains itself.

Should I choose the lowest ADU bid?

Only if it is the lowest for the same scope. A bid that excludes site work, fees or design is not cheaper; it is shorter.

What should an ADU bid include?

A written scope, the size, a construction price, design and permit costs, site work and utilities, fees, allowances and exclusions, a schedule, a payment schedule tied to completed work, the CSLB licence number, insurance, warranty, and the conditions the lot must clear.

How do I check an ADU contractor's licence in California?

Search the licence number or business name at cslb.ca.gov. The record shows licence status, classification, bond, workers' compensation status and any disclosed complaints.

How much deposit can a contractor ask for in California?

State law caps the down payment on a home-improvement contract. We do not print the figure because it is the kind of number that should come from the regulator: the current cap is published by the Contractors State License Board at cslb.ca.gov.

Can ADU Build Works get me quotes?

Not today. No builder is signed to our roster as of November 2026. You can still run the lot check, save your brief, and use it with any builder.

Check your lot

Get the brief that every builder can price

Type your address and tap twice. You get a plain-language verdict on screen, then a one-page brief with this comparison sheet attached — print it or save it. We ask for contact details only if you choose to save your brief. No builders are signed to our roster yet, so no quotes are available today and no builder will contact you.

Check my lot

FREE · FAST VERDICT

Step 1 of 2 — your address, what kind of home it is, and what you want to build. Two taps. That is enough for a first verdict; sharpen it afterwards only if you want to.

Your address is looked up with the US Census geocoder and FEMA flood maps to find your jurisdiction. Nothing about you is stored unless you choose to store your brief after your verdict. Privacy

Sizes in the fast verdict are rule caps for your town. Tell us your lot size afterwards, in “Sharpen your verdict”, and we'll check what your lot can actually hold.

ADU Build Works · Lot planSheet A-1 · Your verdict

Fast verdict — preliminary

Your lot looks workable.

    Confidence: preliminary — inferred from your address and answers, not yet confirmed by a site check or a municipal record pull. Nothing here is a permit approval or a guarantee.

    Save your brief

    Four quick things: your name, how to reach you, whether the home is yours, and your OK to contact you. Nothing is stored until you tap the button. Your verdict stays on this page either way — the full plan is just below.

    Roster status, plainly: our founding roster is enrolling and no contractors are signed yet. Early projects are first in line for matching when seats fill — you may then receive up to 2–3 comparable quotes and choose. No quotes are available today, and we will not pretend otherwise.

    View rules: The 2027 view re-reads every row under the rules that start Jan 1, 2027 — rows that change are badged.

    Every type, answered — not just the one you picked

    True cost — the planning band, the fees on record, and what the band leaves out

    Not in the band — budget these separately; no honest source lets us put a number on them for your lot, so none is invented:

      How long until someone can move in?

      Dates that change this decision

        What the permit record shows

        What would change this answer

        Lay your quotes side by side

        Print this sheet and write each contractor's figures in a column. Every row is something a comparable bid has to state; a blank in a quote is a question for that contractor, not a saving. The first column is your brief, filled from your answers.

        Line every quote must stateYour briefQuote AQuote BQuote C

        Check each contractor's licence number on the Contractors State License Board's public lookup (cslb.ca.gov) before you compare prices. Figures in your brief are the rule caps and planning estimates shown above, not bids.

        Make your verdict more exact (optional)

        All of these are optional. Answer any you know and your verdict above updates straight away. You can skip every one of them.

        Skip these — save my brief ↑